Cost 1-10
Cost 1-10 custom fields show any currency format information related to a task or a
resource. For example, you add total estimated cost of a task by viewing custom
field Cost and you would like to track the high and low estimated cost for a
task or project.
If you created custom fields Cost 1–10 when
you set up VIP Task Manager Professional, you can rename one of these custom
fields, for example, Cost 1 to "High Est. Cost" and add the highest value for
this custom field or rename custom field "Cost 2" to "Low Est. Cost" and enter
the lowest value for this custom field.
To create
custom fields Cost 1-10 please follow the steps below:
1. Go to: Tools/Custom fields and press "Ins"
button
2. in "Title" field enter "Cost 1", "Cost 2" or "Cost 3", etc.
3. in "Code" field enter "cf_cost_1", cf_cost_2" or "cf_cost_3", etc.
4. in "Type" field select "Currency" and click "Ok" button
5. to display the value of custom fields Cost
1-10 on Task List or Task Tree please go to Task List or Task Tree, click Task
List Columns or Task Tree Columns button and check the custom field "Cost 1", "Cost 2" or "Cost 3", etc.
6. to enter value of custom fields Cost 1-10
please do the following:
- Open a task and go to Custom Fields tab
- Enter
the value for custom field "Cost 1",
"Cost 2" or
"Cost 3",
etc. and click "Ok" button. For example, if you renamed "Cost 1" custom field to "High Est.
Cost" and the highest estimated cost for a task is $1000 USD enter the value
for this custom field.
|