The
following workflow allows to track the statuses of
simple tasks, i.e. when Administrator or the owner of the task does not need to
verify the results of performed work over the course of task lifecycle. The
example of such task can be as follows: the sales manager needs to remind the
customer to read the quotation.
- Create
Task status
"Create" shows that the responsible resource initiated the task.
- Work
in Progress
Task Status
"Work in Progress" is displayed if the assigned resource is executing the task
and it hasn’t been finished yet.
- Complete
The task is
marked with the status "Complete" if the assigned resource successfully
executed the task.
Task statuses of Custom Workflow 56 on Task List
To create
custom workflow using the statuses described above, please follow the steps
below:
- Go to: Tools/Custom workflow
- Click "New Workflow" button.
- In Name field enter custom
field name, for example, "Workflow 56".
- Click "Ins" button, enter the
status name "Create" in Name field and click "Ok" button.
- Add other statuses: "Work in
Progress" and "Complete".